Status
No final report
Assembly
House of Representatives
Opened
19 July 2023
Assembly term
10th National Assembly (2023–2027)
Committee
Not stated in the record
Sum at issue
Not stated
Subject
Contracts and procurement
Without a report for
1,211 days
On a motion by Yusuf Shittu Galambi, the House of Representatives mandated its Committee on Works to investigate the abandonment of Section 1 of the Kano–Maiduguri road, awarded to Dantata and Sawoe Construction Company, while the other four sections of the dualization contract approved in 2006 had long been completed, and to report within three weeks.
What the record shows
- 19 July 2023Probe opened.
- As of 11 November 2026No final report of this probe has been found on the public record.
Opened more than 120 days ago, and no final report of the committee has been found on the public record. Interim reports and hearings are shown where known. Know of a report, hearing or outcome missing here? Send a correction.